The Franklin County Engineer's Office (FCEO) has provided us with an updated schedule for the Safe Routes to School project in Brookside. The project is scheduled to resume next Monday, October 27, and follow these steps:
- Week 1: Storm sewer installation
- Week 2: Sidewalk grading, preparation, and forming
- Week 3: Pouring of sidewalk and curb ramps, and replacement of driveways
- Week 4: Restoring, including grading, topsoil, seeding, and mulching.
The schedule is subject to change due to weather, labor, material, equipment, or other unforeseen construction issues.
Please contact Road Superintendent Ian Warren with any questions about the project: iwarren@perrytwp.org or 614-889-8781