Perry Township has received an updated schedule for the resurfacing project on Circle on the Green and Greenside Ln. The updated schedule is as follows:
- 8/14: Pavement milling. Work should be completed on the same day.
- 8/15: Fibermat will be implemented. Fibermat is a stress absorbing interlayer used to waterproof and seal small cracks or imperfections in the asphalt before the surface course is installed.
- 8/18: The final asphalt surface course will be laid down.
Additionally, Road Superintendent Ian Warren will contact Aqua in mid-August to have DLC Equipment Company return to repair yards that have settled and/or reseed grass that did not take following the waterline project. The heat during summer months makes it not a good time for grass seed to take, so the objective is to have additional yard restoration take place once the extreme has passed.
If you have any questions, please contact Road Superintendent Ian Warren: iwarren@perrytwp.org or 614-889-8171.